How to prepare your plot for fence installation
Before your fence goes in, there are six things to check: the plot boundaries, the utilities running underground, the strip where the fence will stand, the cabling to the driveway and pedestrian gates, the paperwork, and access for the delivery. Overlook any one of them and it will cost you more later than fitting the panels does, and some have to be dealt with before the paving and lawn go down.
1. Establish the plot boundaries
This is the point that causes problems most often. A fence goes on the boundary or right next to it, so you need to be certain where the boundary is. If the boundary markers can’t be seen, the plot was divided long ago or there’s a dispute with a neighbour, bring in a land surveyor first. Correcting a fence put up out of line costs more than a surveyor’s visit.
2. Check what’s underground
Water, electricity, gas and sewer connections and telecoms cables along the fence line are a real risk when digging foundations. Get hold of the utility connection plans and mark the routes on the ground. The crew needs to know where to dig with care.
3. Clear and level the strip for the fence
- Remove bushes, roots and rubble from the installation line.
- On steep slopes, decide whether the fence should step down or follow the slope.
- Mark the boundary points and the fence line on the ground, e.g. with pegs and string.
4. Plan the cabling to the driveway and pedestrian gates
If the gate is to be automated, the power supply and the ducts for the motor, photocell and intercom cables must be in the ground before the fence is installed and before the paving goes down. At this stage, running them is simple. Adding them later means lifting paving and makeshift solutions.
5. Paperwork
A fence taller than 2.20 m requires a notification (zgłoszenie) to the county office (starostwo); a lower one needs neither a notification nor a permit. The local zoning plan (MPZP) may also restrict the height, the material or how see-through the fence is. The details are in a separate post on the formalities. It’s better to check this before installation than to alter a finished fence.
6. Access and space for materials
This is the one people forget most often. Panels, posts and the gate arrive on a pallet or in bundles several metres long and need space to be unloaded close to the fence line. If access is blocked by stored rubble, the finishing trades’ vehicles or a freshly sown lawn, installation takes longer because the materials have to be carried in by hand. Before installation, decide which way the delivery will come in and where the components can be safely laid down for a day or two.
When the posts are being concreted, it also helps to have access to water and electricity (on a building site, even from a generator). Small things like these decide whether the crew finishes on schedule.
It’s best to work through this list before the site survey. Then all that’s left to decide on site is the design, the height and where the gate goes.
Frequently asked questions
What should I do with an old fence on the line of the new one?
Take it down before installation, including the concrete posts and foundations. Old foundations get in the way of the new holes, and pulling them out on installation day holds the crew up. Agree who will handle the demolition and removal before the site survey.
Does my neighbour have to agree to the fence?
A fence standing entirely on your own plot doesn’t need your neighbour’s consent. A fence centred on the boundary line stands partly on their land, so their consent is needed. Your neighbour doesn’t have to contribute to the cost of building it; any split is purely by agreement. Only the upkeep of a fence standing on the boundary is shared (Article 154 of the Civil Code, Kodeks cywilny).
When is the best time to start preparing?
Alongside the external finishing work, before the paving is laid and the lawn put down. The cabling to the driveway and pedestrian gates (power, intercom) must be in the ground before the surface goes down, and the material delivery needs clear access.
Legal position as of October 2026. General information, not legal advice.
Quote after a site survey
We’ll come out for a site survey and prepare a quote within 7 working days of it. There is a charge for the site survey because it covers travel, measurements including levels, and choosing the system; the cost is agreed individually and deducted from your order. Manufacturer’s warranty – Wiśniowski fences come with an anti-corrosion warranty of up to 10 years. The terms of our own installation warranty are set out in the quotation.