How long a fence takes, from site survey to installation
Getting a fence put up involves four stages: site survey and quote, manufacturing, foundations, installation. Each takes its own time, and any of them can be held up by a change of mind or a plot that isn’t ready. Most misunderstandings come from confusing two dates: how long it takes to make the components, and when the crew can get on site.
Site survey and quote
Once you’ve been in touch, we arrange a site survey at the property. There is a charge for the site survey, which covers travel, measurements including levels and choosing the system; the cost is agreed individually and deducted from your order. We prepare the quote within 7 working days of the survey. This is when the decisions get made: design, colour, height, gate, automation. The sooner they’re made, the sooner manufacturing starts.
Manufacturing
The panels, posts, driveway gate and pedestrian gate are made to measure by the manufacturer. The manufacturer gives an approximate lead time when confirming the order, and it depends on the system and colour: standard colours (e.g. anthracite RAL 7016) are usually quicker, while non-standard colours and textures take longer. At the height of the season (spring–summer), manufacturers’ queues grow, so an order placed in April gets a different lead time from the same order placed in January.
Foundations and plinth
Posts are set in concrete, at least down to frost depth (1.0 m around Piaseczno). The concrete has to cure before the panels go on, and for a sliding gate the footing for the motor and counterbalance takes longer: manufacturers give about 14 days. A masonry plinth wall adds time for building and finishing it. Frost stops concrete work, so in winter installation is only possible when the weather allows.
Installing the panels, gates and automation
Fitting the panels onto finished posts goes quickly: a typical front fence with a gate takes the installation team a few days, depending on its length and the terrain. The automation is commissioned last, once a qualified electrician has connected 230 V power at the gate: motor, photocells, warning light, remotes.
What most often causes delays
- Changing your mind after the order is placed (a different colour, a different height): manufacturing starts again from scratch.
- A plot that isn’t ready: boundary not marked out, rubble along the fence line, groundwork unfinished.
- No power at the gate on the day the automation is due to be commissioned.
- Weather: prolonged frost or heavy rain halts foundation work.
We give a date after the site survey. By then we know the system, the colour and whether the plot is ready, and those three things decide the schedule.
What installation looks like
On the first day, the crew marks out the line, digs or augers the post holes and concretes the posts in. There’s no fence to see yet, but it’s the most important stage: a crooked post stays crooked for years. Once the concrete has cured, the panels go up, usually anything from a dozen to several dozen metres a day, depending on the system and terrain. The driveway gate and pedestrian gate go in last, and the automation once there is power at the post.
At handover, the driveway gate, pedestrian gate, photocells and remotes are checked; the motor manual stays with the owner. Minor marks left by the groundwork around the posts grow over within a season.
Frequently asked questions
Do I need to be there during installation?
Not the whole time. You need to be there at the start (to confirm the fence line and give access to the plot and power) and at handover (commissioning the automation, remotes).
What if something isn’t right after installation?
Let us know straight away. Adjusting the pedestrian gate, aligning the photocells and measuring the motor forces is a job for a service technician; don’t change the force settings yourself. Product defects are covered by the manufacturer’s warranty, and the terms of our installation warranty are set out in the offer. The warranty does not limit the buyer’s statutory rights.
Quote after a site survey
We’ll come out for a site survey and prepare a quote within 7 working days of it. There is a charge for the site survey because it covers travel, measurements including levels, and choosing the system; the cost is agreed individually and deducted from your order. Manufacturer’s warranty – Wiśniowski fences come with an anti-corrosion warranty of up to 10 years. The terms of our own installation warranty are set out in the quotation.