How deep to set fence posts
Posts carry the weight of the panels and the wind load down into the ground. If they sink or lean after winter, the panels stop lining up and the gate stops closing. Below: how deep to dig around Piaseczno, what post spacing to use, how to concrete posts in, and how the foundation for gate posts differs.
How deep to set a post
The rule of thumb is that a post should go into the ground to about 1/3 of its height above ground, but no shallower than frost depth. In Masovia, including the Piaseczno area, frost reaches down to 1.0 m (deeper in the north-east of the country). For fences 1.5–1.8 m high, a post foundation should therefore be at least 1.0 m deep.
With a low fence (up to 1.2 m), contractors often go shallower, but frost acts on a shallow foundation just the same. It’s safer to stick to 1.0 m here as well. The taller and heavier the panel, the deeper and wider you need to dig: a taller post acts as a lever and pulls harder on its foundation.
Post spacing
The spacing follows from the panel size. Mesh panels and aluminium panels are usually installed at 2.0–2.5 m post centres. With wider, heavier panels, it’s better to space the posts closer. Spacing that is too wide causes sagging and overloads the fixings, which is why the system manufacturer’s guidelines apply.
Concreting step by step
- Mark out the fence line and post spacing. A string line and a few pegs will save you plenty of corrections.
- Dig the holes down to frost depth (at least 1.0 m around Piaseczno) and put a few centimetres of gravel in the bottom for drainage.
- Stand the post in the hole, level it in two planes and brace it (wedges, props).
- Fill with concrete of at least class C16/20 and shape the top so that water runs away from the post.
- Keep checking that it’s plumb until the concrete has set. Fresh concrete can pull a post out of line.
Concrete starts to set within the first few hours and reaches full strength after about 28 days. The panels can go on after a few days, once the posts are held rigidly. The gate needs a longer wait: the footing for the motor and the gate posts must cure first, and manufacturers give about 14 days.
The most common mistakes
- Too shallow: frost lifts the post and after winter the gate no longer closes.
- No drainage: water sits around the post and cracks the foundation in winter.
- Fitting panels on fresh concrete: the load shifts a post that hasn’t set yet.
Foundations are the easiest place to save money and the most expensive to put right later. Straightening a crooked post means breaking out the foundation, digging a new hole and refitting the panels.
Posts for driveway and pedestrian gates
A post next to a fence panel only carries the weight of the panel and the wind. A gate post works differently: with a sliding gate it takes the load from the carriages and motor, and with a double swing gate it takes constant jolts from opening and closing a leaf weighing several hundred kilograms. That’s why gate posts get a separate, larger foundation, reinforced and deeper than for the rest of the fence. With a sliding gate, there are posts on both sides of the entrance, and on the side the gate slides back to, a footing is built for the motor and the leaf’s counterbalance section. The footing dimensions are given in the gate manufacturer’s instructions.
Ducts for the automation cables have to be left in the gate foundation from the start, before the concrete sets. Adding them later means breaking into the concrete and a less tidy cable run.
- Gate posts: a wider and deeper foundation than for the fence panels, ideally reinforced.
- Sliding gate: a footing for the motor and counterbalance, in line with the posts, as per the manufacturer’s instructions.
- Ducts for power and photocells set into the foundation from the start.
Frequently asked questions
Can posts be set without concrete, on a driven ground spike?
With light, low fences on firm ground, it can sometimes work. Aluminium and steel fences with solid panels, and gates, need concrete: a solid panel catches the wind like a sail, and a driven spike goes out of plumb after the first frosts.
Do the posts have to be perfectly in line?
Yes, the look of the whole fence depends on it. Before concreting, a string line is stretched out and the posts are set with a spirit level in two planes. Once the concrete has set, any correction means breaking out the foundation.
Quote after a site survey
We’ll come out for a site survey and prepare a quote within 7 working days of it. There is a charge for the site survey because it covers travel, measurements including levels, and choosing the system; the cost is agreed individually and deducted from your order. Manufacturer’s warranty – Wiśniowski fences come with an anti-corrosion warranty of up to 10 years. The terms of our own installation warranty are set out in the quotation.
Request a quote